☀ Solar · Under construction
Sunčana elektrana Čakovec
11,02 MWp
1.058 MWh/mo
CapacityKw = 11.024 MW installed (DC), AcKw = 8.5 MW connection figure, per the source's own two-figure statement. No investment figure is published on the source page for this plant, so BuildCostEur is left NULL rather than invented. An environmental-assessment filing locates the plant on cadastral parcels 3524/1, 3524/3 and 3524/4 k.o. Čakovec -- not separately geocoded here, so Lat/Lng use the Čakovec city-center coordinate instead (a coarser estimate than most other rows in this import). CommissionYear left NULL (still under construction).
Izvor podataka: https://www.hep.hr/projekti/obnovljivi-izvori-energije/neintegrirane-sunceve-elektrane/3422
Strane i prijave uloga
1| Uloga | Tvrtka | Status | Preuzeo/la | Radnje |
|---|---|---|---|---|
| Vlasnik | HEP | Unclaimed |