☀ Solar · Operational
Sunčana elektrana Donja Dubrava
12,35 MWp
1.292 MWh/mo
Pušteno u pogon
2023
Trošak izgradnje
€7.700.000
Built adjacent to HEP's existing HE Dubrava hydro plant, on the Prelog-Donja Dubrava road, ~17.6 ha. CapacityKw = 12.35 MW installed (DC), AcKw = 9.9 MW connection figure, per the source's own two-figure statement. CO2 avoidance estimated at ~167,000 tons over a 30-year lifetime per the source page; independent press coverage described it as the largest PV plant in Croatia at commissioning. Coordinates are municipality-level (Sveta Marija) -- no more precise geocode for the actual parcel (near HE Dubrava, on the Prelog-Donja Dubrava road) was found during this research pass.
Izvor podataka: https://www.hep.hr/projekti/obnovljivi-izvori-energije/neintegrirane-sunceve-elektrane/3422
Strane i prijave uloga
1| Uloga | Tvrtka | Status | Preuzeo/la | Radnje |
|---|---|---|---|---|
| Vlasnik | HEP | Unclaimed |