3 MW
1.531 MWh/mo
Pušteno u pogon
2018
Financiranje
KfW bank loan
Toplinski kapacitet
10.000 kW
Učinkovitost
73%
Gorivo
Forest biomass (šumska biomasa)
5.489 MWh/mo heat
High-efficiency cogeneration (combined heat + power) on forest biomass fuel, secured via long-term supply contracts. Primary purpose is technological steam for industrial consumers plus district heating for the city of Osijek. Sited next to the existing TE-TO Osijek plant. Has povlašteni proizvođač (privileged/subsidised producer) status with a guaranteed feed-in tariff for 14 years, per Croatia's Ordinance on privileged electricity producer status -- unlike VE Korlat, which explicitly does not. Built 2017, use permit obtained 2018. Build cost (BuildCostEur) left blank -- HEP only publishes a combined EUR 35M figure for both BE-TO Osijek + BE-TO Sisak together, never split per plant, so a per-plant number here would be a fabricated 50/50 guess.
Izvor podataka: https://www.hep.hr/projekti/obnovljivi-izvori-energije/be-to-bioelektrane-toplane/249
Strane i prijave uloga
2| Uloga | Tvrtka | Status | Preuzeo/la | Radnje |
|---|---|---|---|---|
| EPC izvođač | Đuro Đaković Holding + HOST B.V. (Netherlands) consortium | Unclaimed | ||
| Vlasnik | HEP | Unclaimed |