3,5 MWp
375 MWh/mo
Pušteno u pogon
2020
Trošak izgradnje
€6.500.000
11,200 x 340 Wp modules (Solvis); 5 x 720 kW inverters (Končar); 1 MW / 1.44 MWh battery storage (the first of its size in Croatia), stored here as BatteryKwh. Source states >4.5M kWh/yr ("at least", not an exact figure) -- MonthlyMwh uses the 4.5M floor. BuildCostEur SUMS the source's two published investment figures for this one project: EUR 4.2M (plant) + EUR 2.3M (battery) = EUR 6.5M -- see header note; there is no separate battery-cost column. CapacityKw uses the AC figure; no separate DC/nameplate figure is published. Sited on Griževa glavica hill near Žena Glava, ~3.6 km SW of Vis town / 4.8 km E of Komiža -- first large solar plant built on a Croatian island, and the largest solar plant in Croatia at commissioning (2020). Coordinates: a corner node of OpenStreetMap way 773386641 ("Sunčana elektrana Vis" on openinframap.org), independent of HEP's own site and consistent with the stated hilltop location relative to Vis town.
Izvor podataka: https://www.hep.hr/projekti/obnovljivi-izvori-energije/neintegrirane-sunceve-elektrane/3422
Strane i prijave uloga
2| Uloga | Tvrtka | Status | Preuzeo/la | Radnje |
|---|---|---|---|---|
| EPC izvođač | Solvis d.o.o. | Unclaimed | ||
| Vlasnik | HEP | Unclaimed |