🌀 Wind · Commissioning
Vjetroelektrana Bruvno
45 MW
Priključak na mrežu
45 MW
HOPS official monthly report: installed 45 MW, approved connection 45 MW at 110 kV. HOPS status is "testing operation / pokusni rad" -- built and grid-connected but not yet in full commercial operation (Trajni pogon not yet granted); mapped to Status='Commissioning' here, this DB's dedicated bucket for that lifecycle state. No commissioning year given by HOPS yet -- CommissionYear left NULL. COORDINATE FLAG: no site-level coordinate found -- the 2019 elaborat (mingo.gov.hr) places the site in KO Rudopolje Bruvanjsko/KO Bruvno but its PDF exceeded this research pass's fetch-size limit. Coordinate stored here is the Bruvno settlement centroid (44°24'07"N 15°53'45"E) as the best available Approximate estimate. Long, stalled development history: project originated 2007-2009, originally sized 45-54 MW across 18 turbines, later optimized to 15 turbines x 3 MW = 45 MW (matching HOPS's installed figure exactly); as of a 2020-era search snapshot the project reportedly lacked valid building/connection permits, but HOPS's current report confirms it has since been built and grid-connected in test operation -- the intervening progress was not independently traced in this research pass. No annual-production figure found (plant not yet in full operation) -- MonthlyMwh left NULL. No build-cost figure confirmed (a Nacional.hr headline referencing a "41 million kuna HEP investment" in this project could not be read -- 403-blocked -- and was NOT incorporated; flagged as an unread lead). Owner: VJETROELEKTRANA BRUVNO d.o.o. (OIB 64316502032, MB 02277352, Park sv. Jurja 1, Gračac, founded 2007) -- owned by 5 natural persons: Dragutin Kamenski, Josip Galić, Mirjana Igrec, Olivera Babić, Tonći Panza. NOTABLE OVERLAP: Tonći Panza is also a co-owner of Adria Wind Power d.o.o. (owner of VE Ravne 1, already in this DB per migration 048) -- a real cross-plant ownership link, not a data error. This fininfo.hr ownership snapshot has no confirmed date; given the project's long stall before reaching test operation, a fresh registry check is recommended before treating this as final. No Hrote match found for this producer.
Izvor podataka: https://mingo.gov.hr/UserDocsImages/UPRAVA-ZA-PROCJENU-UTJECAJA-NA-OKOLIS-ODRZIVO-GOSPODARENJE-OTPADOM/Opuo/09_09_2019_Elaborat_VE_Bruvno.pdf
Izvor podataka: https://www.fininfo.hr/Poduzece/Pregled/vjetroelektrana-bruvno/Detaljno/92519
Izvor podataka: https://infobiz.fina.hr/tvrtka/vjetroelektrana-bruvno-d-o-o/OIB-64316502032
Strane i prijave uloga
1| Uloga | Tvrtka | Status | Preuzeo/la | Radnje |
|---|---|---|---|---|
| Vlasnik | VJETROELEKTRANA BRUVNO d.o.o. | Unclaimed |