36,8 MW
7.038 MWh/mo
Pušteno u pogon
1968
Tip postrojenja
Reservoir
Turbina
Francis
Broj jedinica
2
Pad
224,5 m
Protok
21,00 m³/s
Volumen akumulacije
0,47 hm³
Centar proizvodnje Zapad
High-pressure derivation plant on the Rjecina, powerhouse at 5m elevation practically in central Rijeka near the coast; intake several km upstream at 229.5m elevation (gross head 224.5m calculated from these two stated elevations, not a directly published head figure). 2 vertical- shaft Francis units, 18.4 MW each. Hourly-regulation reservoir (0.47 hm3) at the Valici intake dam near Grohovo. Average annual production ~84.45 GWh. Also has a 350 kVA house diesel generator. Provides ancillary services (tertiary regulation, black start, island operation). Organizationally part of GHE Vinodol, under Centar proizvodnje Zapad. Coordinates are a town-level estimate (Rijeka), not plant-exact.
Izvor podataka: https://www.hep.hr/proizvodnja/hidroelektrane-1528/pp-he-zapad/he-rijeka/1535
Strane i prijave uloga
1| Uloga | Tvrtka | Status | Preuzeo/la | Radnje |
|---|---|---|---|---|
| Vlasnik | HEP | Unclaimed |